top of page

E. Broussard/Robley Drive Roundabout

STATUS

Future Project

COST

$2,750,000.00

E. Broussard/Robley Drive Roundabout

PROJECT CATEGORY

Intersection Improvements
Construction Start
06/01/24
Construction Complete
06/01/25

Public Works Project Number: 1805

Project Length (miles): 0.5

Parish District: 4

Construction Estimate: $2,500,000.00

Project Cost: $2,750,000.00

Project Type: Traffic, Roads, & Bridges

Designer: Fenstermaker & Associates, LLC


 

PROJECT OVERVIEW

The E. Broussard at Robley Dr. Roundabout project involves the construction of a new concrete roundabout at the intersection of E. Broussard Road and Robley Drive. This proposed roundabout will further enhance traffic flow and safety of the intersection. By replacing the existing stop-controlled intersection with a roundabout, the following benefits can be felt: a reduction in serious crashes due to a reduction of conflict points, an increase in traffic capacity, improved operational performance, promotion of lower speeds, traffic calming, and a decrease in wait times.


 

DRAINAGE AND GREEN INFRASTRUCTURE CONSIDERATIONS

Existing drainage for the project area utilizes an open (ditch) system. The upgraded corridor will utilize a closed (sub-surface) system with curb and gutter to collect and transport water runoff quickly to a stormwater system which will aid in the reduction of flooding. Throughout the project, the construction team will carefully monitor the drainage system to ensure that it is functioning correctly. They will also make any necessary adjustments to the system to ensure that it is optimized for the area's drainage needs.


 

ENVIRONMENTAL CONSIDERATIONS

Minimal environmental considerations have been identified and must be reviewed and potentially addressed.

*Note that this is not exhaustive of possible future environmental considerations


 

UTILITY CONSIDERATIONS

A preliminary assessment of the project area is provided for the utilities listed below. Potential utility relocation costs will be included in the project budget if the infrastructure is located within the utility’s own servitude.



 

RIGHT OF WAY CONSIDERATIONS

The project at hand involves significant right-of-way acquisition, utility easements, and construction servitudes, which are necessary for the construction of a new roundabout.

bottom of page